If you walked the paved loop at Vistoso Trails Nature Preserve in September, you might have heard the pond would be back by the holidays. The Town Manager's September report to Council said the project should finish "before the end of this calendar year." That date no longer holds. A wet fall slowed the work, an old liner turned out to be a different material than expected, and the grass around the 2.5-acre basin has to wait for the right planting season.
At the October 7 Town Council meeting, Public Works Director and Town Engineer Paul Keesler said the project had been on track for January 31, 2027, until a recent storm. He now expects mid-February. According to ILoveOV's account of the meeting, the contract deadline is May 11, 2027, and the sod will go in last, close to that date. Construction could wrap up in mid-February, but the finished area with its grass comes closer to May.
A Pond the Town Almost Didn't Rebuild
The basin you're walking past was a water feature on the old Vistoso golf course, which closed in 2018. The Conservation Fund bought the property in February 2022 and donated it to Oro Valley that July under a conservation easement. The Town credits more than 600 community members, organized by Preserve Vistoso, with funding most of the purchase.
For a while, the pond wasn't going to come back at all. In April 2024, Council voted unanimously to turn the old basin along W. Vistoso Highlands Drive into a "Desert Garden" by filling and reshaping it. In December 2024, Council asked its consultant, Kimley-Horn, to price a pond option. On April 16, 2025, Council reversed course 4–2 and directed staff to restore the 2.5-acre pond using reclaimed water. As reported by the Explorer, Mayor Joe Winfield voted no, citing water conservation, long-term cost and sustainability. Vice Mayor Melanie Barrett voted yes and argued the costs of the options weren't very different.
In April 2026, Council approved $461,399 from General Fund Contingency, bringing the project total to $2,033,939. That covered the base bid for the pond and a memorial garden, plus an alternate bid for a parking lot and an accessible connection to the existing path. Contractor KE&G started construction on August 10.
What the Fall Rains Did to the Schedule
The Town posts a weekly update on its pond project page. Read in order, the updates show how the work slowed down:
- Week of August 19: KE&G came back to keep grading after a week of rain delays.
- Week of September 9: Crews were finishing final grading. Liner installation was expected in about two weeks.
- Week of September 23: The wet well had been built ahead of schedule and was due in two to three weeks.
- Week of September 30: Rain caused another delay while the ground dried. The wet well was then expected to be installed by mid-October.
- Week of October 7: After heavy rain, crews pumped water out of the basin and spread mud around so it would dry more evenly. The pump skid had arrived.
- Week of October 21: The pond was still drying. Crews were grading the future turf area and sidewalks while they waited for the ground to firm up enough for heavy equipment to install the wet well and pipes.
The liner was promised "in approximately two weeks" in early September, and it still hadn't gone in by late October. Rain wasn't the only reason. The old liner turned out to be plastic, not clay, and the supplier of the new liner wants more of it removed. Keesler said he expects a change order for that work and told residents the project isn't stopping.
Why the Grass Comes Last
The October 7 meeting also decided what the finished area will look like. Council voted 7–0 to allocate $500,000 from contingency to finish the accessible trails around the pond, along with the grading, irrigation and turf. Staff had estimated the added cost at about $425,000 and suggested $500,000 for a cushion, with any unspent money returning to the budget. Ten people spoke during public comment, and all of them urged Council to finish the project. Several argued that stopping now would cost more later and leave the site looking abandoned.
The turf is why the calendar runs into spring. Matt Wood, chair of the Parks and Recreation Advisory Board, told Council that Bermuda sod does best when laid in spring. That fits Keesler's plan to lay sod last, around the May 11, 2027 contract deadline. The Town's October 7 presentation lists the work in this order:
| Phase | Where it stands |
|---|---|
| Mobilization and demolition | Done. Old concrete walls and bulkhead removed in August |
| Grading | Delayed by rain into late October |
| Pond liner | Waiting on the basin to dry and on extra removal of the old liner |
| Pump station and mechanical | Pump skid on site, wet well next |
| Memorial area | Scheduled |
| Parking lot | Scheduled |
| Concrete flatwork | Sidewalks and ramada pads being graded |
| Closeout, then sod | Sod near the May 11, 2027 contract end |
The presentation said more than three months of schedule float remained. That's room for more weather delays before the contract deadline itself is at risk.
What Will Be There When It's Finished
The basin will hold reclaimed water drawn from an existing connection through a pump, filter and wet well. Diffusers on the bottom will keep the water moving and oxygenated so it doesn't sit stagnant. The new liner has several protective layers. The pond will fill slowly at first to protect the liner, and a level sensor will time the fill around other demands on the town's reclaimed water system. An 8-foot concrete trail will circle the pond.
At the October 7 meeting, Parks and Recreation Director Rosalyn Epting listed the rest of the finished area:
- The pond and its trail loop
- Turf and plantings
- Six ramadas
- Benches and trash cans
- Two added trails
She said it would look like the Sonoran Desert, not a golf course.
The Adam Zimerman Memorial Garden will sit near the pond. The Explorer reported that it honors an avid cyclist who used the preserve and is funded by a home donated to the Town in his memory. A separate Explorer story said the plan includes shade trees, seating stones, a bike rack, a commemorative plaque and a water station with a bottle filler. The Town's October presentation shows the home sold for $270,000 and lists a separate change order for the memorial's drain line and water fountain.
What Isn't Funded Yet
Some of the extras haven't been approved. The Town hoped to pay for more amenities with a Land and Water Conservation Fund grant: $407,895 from the grant, matched by $407,895 from the Town. On October 7, Council voted 7–0 to send the application back to staff for revisions instead of approving it. Epting said the 0.8-acre pond lawn would come out of the application, since the contingency vote now covers turf. Costs for trees, the pond trail and restroom work have gone up. Exercise stations along the trail would qualify.
One request may matter more than the ramadas to people who walk the loop often. A resident asked Council to move faster on the restroom near the former driving range, which has no electrical service and needs ADA upgrades. Epting said Public Works has plans and needs to update the costs. Separately, the Town reported a $136,000 invasive plant grant that it matches with volunteer hours. That grant commits the Town to four community weed pulls targeting buffelgrass and Russian thistle across about 10 acres, starting with the former driving range. Dates for those pulls haven't been announced, so check the preserve page for updates.
Walking the Preserve This Winter
Most of the preserve is open while the pond is under construction. The 6.2-mile, eight-foot-wide concrete path still runs past views of the Catalina and Tortolita mountains. It's open dawn to dusk, and temporary parking is at 945 W. Vistoso Highlands Dr. Trails right next to the construction zone are closed, and detour signs guide you around the work. The Town keeps a detour map on the project page. Dogs must be leashed and under control at all times. In October, Town staff were still clearing storm debris along the trail after the heavy rains.
If you'd like a guided walk, Tucson Bird Alliance is leading "Vistoso Trails Nature Preserve with Gerry Hodge" on Monday, November 23, from 8:00 to 10:30 a.m. The group meets at the preserve trailhead parking lot, and you need to register in advance.
If you'd like to follow the project's next steps, the Town posts the pond updates weekly, and the liner is the next milestone. Laurie keeps an eye on what's changing in Oro Valley's parks and trails as closely as she follows the homes around them. For questions about life near the preserve and the streets off Vistoso Highlands Drive, Holiday Homes Family is happy to talk it through. Contact Laurie to Get Started.